Link tasks


To remove a link, select the two linked tasks and then choose Task > Unlink Tasks
.
Project creates a simple finish-to-start task link by default, which means the first task (the predecessor) needs to finish before the second task (the successor) can start.
If you are a Project Online subscriber, you can also select specific tasks to link to using a drop-down box from the Predecessors or Successors column.
Note: The Successor column is not shown by default. To show it, go to the last column in the row, and select Add New Column. Choose Successors.
Selecting links from the drop-down is especially useful if the task you want to link to is not located close to the task you're linking from.
Insert a task between linked tasks
You can set up Project so that when you insert a new task between linked tasks, the new task is automatically linked to the surrounding tasks.
Link tasks in a Network Diagram


Link tasks in a Calendar

Link manually scheduled tasks
When you link a manually scheduled task to another task, Project places the manually scheduled task relative to the other task.
You can configure Project so that a manually scheduled task does not move when you link it to another task:
Learn more about manually and automatically scheduled tasks.
Other ways to link tasks
Change or remove task dependencies
After tasks are linked to create task dependencies, you can easily change or remove the dependencies, if needed, by doing any of the following:
Change the link type of a task dependency
By default, Project links tasks in a finish-to-start dependency. You can, however, easily change the type of task dependency on the Advanced tab of the Task Information dialog box. To open the Task Information dialog box, double-click the name of the task whose link type you want to change.
Note: Double-clicking a link to an external task opens the project containing the task, if the project is available. Externally linked tasks appear dimmed in the task list. If you want to modify the link type for an external task, double-click the externally linked task to open the project that contains the task, and then do the following to modify the linked task. For example, if you linked Task A in Project Z to Task 1 in Project 5, you can modify the link type in the task information for Task 1.

|
|
To change a link type, double-click here. |
Link to a different task
If you have a task that is currently linked to the wrong task, you can easily modify the link so that it reflects the correct dependency.
Tip: To enter lead time, type a negative value in the Lag column, such as –2 for two days of lead time.
Remove all dependencies for a task
If your task is no longer dependent on any other tasks, you can remove all of the task's dependencies at once.
To select multiple tasks that are not listed consecutively, hold down CTRL and select each task. To select tasks that are listed consecutively, select the first task, hold down SHIFT, and then select the last task that you want to select in the list.
The tasks are rescheduled, based on any links to other tasks or constraints.
Note: Removing a task link removes the dependency between two tasks, as indicated by the link lines between the tasks. If you want to change the hierarchical structure of a task or subtask as part of an outline structure for your project, then you need to outdent the task rather than remove the task link.
Remove specific task dependencies
If your task is linked to several tasks and you need to remove specific links while leaving some intact, you can choose which links to remove in the Task Information dialog box.
Turn autolinking on or off
You can configure Project so that when you insert a task among linked tasks, the new task is automatically linked to the surrounding tasks. This is called autolinking. For example, if you have three tasks with finish-to-start links and you add a new task between them, the new task will take on a finish-to-start link with the tasks above and below it.
By default, autolinking is disabled. Follow these steps to turn autolinking on.
Types of tasks
When you link tasks in Project, the default link type is finish-to-start. However, a finish-to-start link does not work in every situation. Project provides the following additional types of task links so that you can model your project realistically:
|
Link type |
|
Example |
|
Description |
|
Finish-to-start (FS) |
|
|
|
The dependent task (B) cannot begin until the task that it depends on (A) is complete. For example, if you have two tasks, "Dig foundation" and "Pour concrete," the "Pour concrete" task cannot begin until the "Dig foundation" task is completed. |
|
Start-to-start (SS) |
|
|
|
The dependent task (B) cannot begin until the task that it depends on (A) begins. The dependent task can start at any time after the task that it depends on begins. The SS link type does not require that both tasks begin at the same time. For example, if you have two tasks, "Pour concrete" and "Level concrete," the "Level concrete" task cannot begin until the "Pour concrete" task begins. |
|
Finish-to-finish (FF) |
|
|
|
The dependent task (B) cannot be completed until the task that it depends on (A) is completed. The dependent task can be completed at any time after the task that it depends on is completed. The FF link type does not require that both tasks be completed at the same time. For example, if you have two tasks, "Add wiring" and "Inspect electrical," the "Inspect electrical" task cannot be completed until the "Add wiring" task is completed. |
|
Start-to-finish (SF) |
|
|
|
The dependent task (B) cannot be completed until the task that it depends on (A) begins. The dependent task can be completed at any time after the task that it depends on begins. The SF link type does not require that the dependent task be completed concurrent with the beginning of the task on which it depends. For example, the roof trusses for your construction project are built off-site. Two of the tasks in your project are "Truss delivery" and "Assemble roof." The "Assemble roof" task cannot be completed until the "Truss delivery" task begins. |
Troubleshooting
If you linked your tasks but the successor task doesn't move, there may be several causes:
For example, if a task has a Start No Earlier Than (SNET) constraint set to July 1, the task is tied to that date and won't be rescheduled to an earlier date, even if its predecessor finishes on June 28 and the successor task could start earlier than July 1.
Here are some possible resolutions: